Decoration order

[index]

(1) Subject Restructuring

(2) Hydropower renovation

(3) package pipe

(4) Tiles

(5) Woodworking (Sakaguchi, etc.)

(6) Brush oil

(7) Wall paint or wallpaper

(8) Install socket panel

(9) Kitchen ceiling

(10) Cabinets

(11) Install the finished product door

(12) Install lamps, sanitary ware, bathroom hardware

(13) Install clothes hangers, window rails

(14) Flooring

(15) Wasteland Cleaning

(16) Furniture, Home Appliances

(17) Curtains and Bedding

[detailed]

(A) Tools are in place and ready

Tape measure (buy 5m, not 3m), calculator, big plate clips (folder list, receipts); In addition, it is best to prepare old towels on the site early (the kind of soft cotton, rubbed with bricks) , plastic bag (wrapped on the pipe interface, can prevent dirt blockage).

(b) Choosing good days and launching artillery

Before the workers enter the court, it is best to measure the corners of the house in person, take them down, mark them clearly, and be sure not to be lazy. Identify the area involved in the renovation process. In particular, the tiling area, wall paint area, wallpaper area, and floor area are defined as the major wall sizes. In particular, it is necessary to design the wall size of the furniture later.

(III) Demolition of the main body to make space more practical

The demolition of the main body is the first one to be put on the project. It mainly includes the demolition of walls, walls, shoveling of wall coverings, demolition of heating (northern), change of steel windows, and so on. After the demolition of the completed garbage, it must be cleared up in time to ensure the cleanliness of the interior, but also to facilitate the construction. At this point, the finished door should be set. At this time, it is best to walk through the cabinets, range hoods, stoves, and water heaters, and try to be sure.

(IV) Hydropower Renovation, Arranging the Use of Each Space

Hydroelectric reform, no regret medicine can eat. Bricks on the wall, a ceiling, and then think of adding sockets can be difficult. Therefore, be sure to determine the exact location of switches, lamps, basins, bathtubs, washing machines, etc. Before the hydropower reform, the cabinet designer should come to the door to make the first measurement and help you determine the power and waterway reconstruction plan. Water heaters, it is also best to send people to design the power, the location of the water inlet and outlet according to your model.

Remind you: On the wall under the basin, it is best to leave the power outlet for the kitchen. The air-conditioning hole and power source should be placed on the wall of the bedside as much as possible to avoid air-conditioning blowing directly to people. Strong electricity and weaknesses need to maintain a space of 20 cm. For example, a distance of 20 cm must be left between the outlet and the cable.

(5) Pack up the tubes and wrap up the unsightly pipes

Considering the wet and damp environment of the kitchen and toilet, the material of the standpipe must not be wood keel! Everyone must be careful, even if the wooden keel brush anti-corrosion coating does not work. Remember to use a light steel keel, or a red brick, on the standpipe. Light steel keel provinces, but the most solid and easy to use is the red brick. At this time you need to buy a good tile, caulking agent, etc.; furniture to be set early, leaving a good duration, at least 15 days or so, generally a month to better time.

To add, don't wrap the pipeline in the place where the access is to be found. In case of seepage, no reason can be found.

(six) tiling, the first thing with a solid texture

Before tiling, buy a floor drain. Note: Floor drains are going to local hypermarkets. To buy a dedicated washing machine or shower floor drain, but also to have deodorant function. After finishing waterproofing and pulling hair, prepare a tiling. The normal tiles pay attention to the water and dry before the tiles are attached; the broken tiles are left for cutting.

Please leave plenty of money before buying bricks. At this time, basins and faucets should be determined, and cabinet designers should be invited to visit the house for the second time. At the same time, paint (mixed or clear), wall paint, lacquer, diluted water, etc. should be purchased.

(seven) oil workers go into battle, scrub scrub brush

There is nothing to say about brushing the walls. Leveling, sanding, and brushing are all effective, and they definitely rely on the craftsmanship of your painter. The good adhesion of the primer can make the wall more smooth, making the topcoat easier to apply and reducing the amount of topcoat used. Moreover, the excellent sealability of the primer makes it effectively resistant to the penetration of alkaline substances in the wall, preventing the precipitation of water-soluble salts and preventing the return of alkali to the walls.

We need to remind everyone that if the walls are to be painted, the color must be noticed. The color of the recall must be lighter than that of the color card. It must not be the same as the color card or deeper than it is. Otherwise, you will regret it. Because at least two coats of paint are used to paint the walls, some of them are still three times. The color of the wall will be deeper than the one layer.

The method of painting is spraying or roller coating. The benevolent sees the person and the wise sees the wisdom. It is said that the effect of spraying is better, but once it is destroyed, it will become difficult to repair the paint. If you do not buy finished products, let the worker master do it.

Note: Any woodwork, even if it is just a mouthwash, must follow this step. The big board sinks and the veneer is veneered before painting. When mixing oil, it is absolutely wrong to brush the oil directly on the big core board. Don’t believe the nonsense of selling Daxin boards individually. There is no problem with brushing oil directly. Remember, if you brush oil directly, it will take a long time for you to crack and remember. Now do oil mixing, no brush, but spray. It is best to let workers spray white on the inside of the door and the meter box.

(8) wallpapers, beautiful walls

After the wall paint is brushed, the oil trader will apply nitro-lacquer to the place where the wallpaper is to be applied. The paint can dry after the next day, and then the master can paste the wallpaper. At the beginning, I was worried that the wallpaper would dirty the painted white wall. I knew it later when I posted it, and the wallpaper was really a special clean job! Worry completely redundant.

Note: Do not open the window for ventilation within 48 hours after the wallpaper has been posted. Let it dry slowly. Say good to the master, if there is an odd place in individual places, trouble him to repair it. At this point, buy the panel, socket, lamp.

(9) Install socket panel

The socket panel can be installed in about half a day.

1, the best outlet to buy with a switch function, especially the kitchen, so that rice cookers, microwave ovens can be removed from the power supply, with the switch to control.

2, although there is a good switch socket, but pay attention to practicality.

According to my observation, the five-hole power supply with switch, three sockets are flat mouth, once your electrical appliances need a round mouth three items, there will be a depressed situation with empty plug socket board. Therefore, multiple sockets must also be used, even if it does not switch control! At this point, you should purchase the ceiling for the bathroom kitchen; at this time, if you need to install Yuba, please buy and install before the ceiling.

(ten) kitchen ceiling, seal the last ugly part

First install the water heater and Yuba, after installation, the ceiling edge can be better half-package water heater, which is more beautiful convergence. It is advisable to buy ceilings from aluminium gussets. Even if they are removed after many years, selling scrap aluminum is worth a lot of money. On the other hand, pvc buckles look good, but the quality and performance are generally the same, and plastic things are worth a few dollars even if they sell waste. Buy buckle board, to ask the price of all-inclusive, do not buckle board, corner to buy. But the installation fee is another calculation.

(11) Installation of cabinets, the birth of a beautiful kitchen

The cabinets are a cooperating project and the hoods, stoves and sinks should be approved in advance. It is best to send it on the same day and install it together with the cabinet. We told the cabinet factory in advance that we would bring the artificial stone countertops with the cut-off appliances and the sinks together. Many silver things cannot be given to manufacturers. It is useful to include a water meter, a pipe, or something.

(12) Installation of finished products

Finished doors should be installed before the floor, mainly because of the complex installation steps, hinges, door locks, door stoppers, door frames, etc., using a large number of tools, such as the first installed floor, bumps are difficult to avoid. My family first installed the floor and then installed the door. There were many small pits on the floor. The meat hurt me.

(13) Installation of drying racks, curtain rods, lamps, sanitary ware, and bathroom hardware

It is recommended that before the installation of the floor, the items with a large amount of scattered ash will be handled one by one.

(14) Installing the floor

Before the floor is installed, we must do a leveling and see that a lot of neighbors do not use the floor leveling, so I also carelessly. Unexpectedly, after the floor was laid, the aisle was gone and it was very depressing. Had to remove it and re-pour it after leveling it with dusting powder. Prepare a little pepper in advance, do not buy the so-called insecticide powder brought by floor workers, let them sprinkle along the kick corner on the line. Workers must be required not to cut the floor in the house, cut in the corridor, and finally clean the corridor.

(15) Wasteland cleaning

The biggest manifestation of cleaning, I think is to clean glass. It is a terrifying thing for a tall building to climb outside and rub it. Followed by the floor waxing, wax to buy their own, cheap and easy to use, but must use a cleaning waxing machine, efficiency is tens of times faster than artificial, hundreds of times. In other respects, I don't think I need to rely too much on cleaning. They also use small blades to scrape here and scrape there, not so much. Therefore, after the cleaning goes, it's best to do a thorough cleaning again. Go to the supermarket to buy a bag of "five clean powder" and get a few old towels. Use an old towel, stained with dried Wu Jie powder, from the mouth to the door, from the tiles to the kick corner, a house, a house of rub, do not be lazy, the result will definitely make you proud.

(16)Appearance of furniture and home appliances

In a new home, furniture bears the brunt. Beds, mattresses, wardrobes, shoe cabinets, sofas, dining tables, etc. Before the furniture enters the market, you should prepare the following items: disposable shoe covers (do not buy poor quality, step on the break), a few boxes of activated carbon, ladders, floor protection film (carrying closet, TV cabinet, etc. protection). If you buy a fabric bed, remind you to see if the fabric can be taken down. Home appliances quickly delivery, tight or not in a hurry to wait and so on. Anyway, electrical appliances are getting more advanced and cheaper.

(seventeen) accessories decoration, home has a taste

With a decorative ornament and beautiful curtains, the soft taste of the home came out. Curtains do not spend too much money on accessories. Curtains and plumb bobs are money that must be added, but lace, cloth clasps, and tassels, which are eight yuan and ten yuan, cost more than twenty yuan per meter. It is not necessary, and it is not necessarily beautiful.

Three trees Paint Nature Floor paint Sockets Wallpapers Windows Furniture Kitchens Kitchen furniture Price features Sofa beds TV wallpapers Glass bricks Cloth Sofa cushions Cabinet doors Kitchen ceilings Fabric sofas Fabric beds Floor tiles Red bricks Glass furniture Fabric sofas Fabric curtains Kitchen cabinet doors White furniture Glass Table Glass Table Glass Door Function Sofa Kitchen Glass Sliding Door Kitchen Bathroom Ceiling Bathroom Tile Bathroom Door Bathroom Tile Color Bathroom Door Size Bathroom Size Bathroom Ceiling Material Bathroom Waterproof Price Toilet Ceiling Overall Toilet Bathroom Design Toilet Waterproof Floor Tile Tile Price Kitchen Tile ld Tile